Past performance

The record, with owners and numbers

Owners, roles, periods, and scope for every contract Basalt has completed since 2024. Contract values, reference contacts, and project-specific detail are furnished on request.

Contract register

Contracts since 2024

All entries verified against executed contracts and final pay documentation on file. Residential and rural work is grouped on the last line. Contract documentation and reference contacts are furnished on request.
ProjectOwner / clientRoleLocationPeriod
Brooklane Apartments Water Services, Phase 2Central Washington UniversityPrimeEllensburg, WA2025 – 2026
Water Street Overlay — ADA Ramp Demolition & PrepCity of Ellensburg / Central PavingSubcontractorEllensburg, WAApr – Sep 2025
Data Center Campus — On-Site Sewage SystemsConfidential (data center)SubcontractorMalaga, WAOct 2024 – Jan 2025
Coastal Farm & Home Supply No. 17 — Yakima EVCSEVSE contractor (private)SubcontractorYakima, WAJune 2026
Kittitas Highway Approach Grading, Phase 1Kittitas County PUD No. 1PrimeKittitas, WANov – Dec 2024
WDFW Region 3 HQ EV Charging StationsWA Dept. of Fish & WildlifePrimeYakima, WAApr – Jun 2026
WDFW Wenatchee District Office EV Charging StationsWA Dept. of Fish & WildlifePrimeWenatchee, WAApr – May 2025
A variety of residential septic systems, foundations, utility, and grading projectsPrivate owners and buildersPrime / SubKittitas County, WA2024 – 2026
Current pursuits. Basalt is pursuing civil construction packages on EV charging sites, data centers, substations, roadways, and utility projects, along with any other scope that fits our capabilities, across Central Washington and the surrounding region. Details on active contracts are available on request.

Project records

Selected detail

Basalt excavator with tiltrotator digging an open water main crossing trench with a dump truck alongside
Public works — prime contractor

Brooklane Apartments Water Services, Phase 2

Basalt’s largest contract to date, delivered as prime contractor for Central Washington University: 130 new HDPE water services with appurtenances, HDPE and C900 mainline extensions, pavement and concrete repair, and final restoration. Executed across an occupied student housing complex, which drove phasing, temporary service continuity, and pedestrian routing. Prevailing wage; Notice of Completion filed May 2026.

Owner
Central Washington University
Role
Prime contractor
Location
Ellensburg, WA
Period
2025 – 2026
Basalt excavator with tiltrotator at a street corner with the curb removed
Federally assisted public works — subcontractor

Water Street Overlay, Main Street to Bender Road

Subcontractor to the paving prime on a City of Ellensburg federal-aid overlay. Demolition of sidewalk, curb and gutter, and pavement, then subgrade preparation for 145 new ADA-compliant curb ramps — block by block on active streets with pedestrian access maintained. Federal-aid compliance included FHWA 1391 reporting and WSDOT 420-004 documentation.

Owner
City of Ellensburg
Role
Subcontractor
Location
Ellensburg, WA
Period
Apr – Sep 2025
Excavator and crew constructing a drainfield on a sand pad below a rock cliff
Data center campus — subcontractor

Data Center Campus — On-Site Sewage Systems

Subcontractor on an OCIP-insured hyperscale data center campus in Malaga. Basalt constructed two complete on-site sewage systems under one contract: the main system serving the data center, and a second system serving the guardhouse at the front entry.

Owner
Confidential
Role
Subcontractor to general contractor
Location
Malaga, WA
Period
Oct 2024 – Jan 2025
Completed asphalt approach with gravel shoulder on a county highway
Public works — prime contractor

Kittitas Highway Approach Grading, Phase 1

Prime contractor for a new commercial approach off Kittitas Highway, built to WSDOT low-volume commercial approach standards: clearing and grubbing, 120 feet of CMP culvert with spall armor end treatment, embankment import, grading and compaction, and HMA surfacing under an approved traffic control plan on an active county roadway.

Owner
Kittitas County PUD No. 1
Role
Prime contractor
Location
Kittitas, WA
Period
Nov – Dec 2024
Conduit trench cut through asphalt with a steel plate and traffic cones
Public works — prime contractor

WDFW EV Charging Stations — Region 3 HQ and Wenatchee District Office

Two competitively bid state public works contracts delivered as prime at operating WDFW facilities. Both carried the same self-performed civil package: demolition, conduit trench and backfill, equipment pads, ADA improvements, patching, and restoration, with electrical and striping by disclosed subcontractors. Both closed with final completion certified by the agency.

Owner
WA Dept. of Fish & Wildlife
Role
Prime contractor
Locations
Yakima and Wenatchee, WA
Periods
Apr – May 2025; Apr – Jun 2026

Residential & rural

Residential and rural work we pursue year-round

A variety of residential septic systems, foundations, utility, and grading projects for private owners and builders in Kittitas County. Client names are withheld out of respect for their privacy.

Excavator backfilling around a newly set precast septic tank
Gravity drainfield trenches with distribution laterals and inspection risers
Newly paved driveway and apron beside a red barn
Excavator and spoil pile at a residential foundation excavation

Field record

Work in progress and at completion

A cross-section of what Basalt actually does: water and sewer utilities, ADA and concrete work, EV charging civil, data center site utilities, septic systems, roadway approaches, mass grading, clearing, and residential site work.

Steelwrist tiltrotator with grading beam attached to a Basalt excavator
Blue HDPE water main with a tapped service saddle in an open trench
Excavator laying black HDPE pipe into an open trench
Excavator loading trench spoil into a dump truck on a wet street
Butt fusion machine joining HDPE water main in an open trench
Excavator with tiltrotator at a street corner with the curb removed
Crew and equipment working on a downtown street under traffic control
Excavator loading removed concrete and asphalt into a dump truck
Tiltrotator grapple lifting a removed concrete panel beside a new sidewalk
Tiltrotator grapple lifting a removed concrete curb panel under traffic control
Wide view of a data center campus with pipe staged and machines working
Excavator working near concrete tanks on a large campus site
Excavator backfilling around a newly set precast septic tank
Drainfield distribution manifold with PVC laterals and a surveyor
Gravity drainfield trenches with distribution laterals
Completed EV charging stall with accessibility striping and bollards
Completed EV charging stalls with bollards and fresh striping
Excavator over a large excavation for a charging equipment pad
Conduit trench cut through asphalt with a steel plate and cones
New paved commercial approach with culvert and crew in high-visibility gear
Culvert end with spall armor protection
Excavator and dump truck cutting and hauling on an open field
Wide graded site with safety fencing under an open sky
Newly paved driveway and apron beside a red barn
Finished gravel drive leading to a shop building
Rock and gravel restored around a new concrete walkway
Excavator clearing a forested lot
Excavator and spoil pile at a residential foundation excavation